Network Diagram



(Click on the image to Enlarge)

Activity Precedence Table

Activity

Immediate Predecessor

Duration Planned (weeks)

Team formation, A

-

1

Determination of nature of business, B

A

1

Planning, Requirement and Design, C

B

3

Design and Programming, D

A

7

Documentation, E

D

1

Draft and Preparation of report, F

B

6

Compilation of report, G

E, F

1

Final checking, H

G

1

Preparation of presentation, I

G

1