Activity Precedence Table
Activity | Immediate Predecessor | Duration Planned (weeks) |
Team formation, A | - | 1 |
Determination of nature of business, B | A | 1 |
Planning, Requirement and Design, C | B | 3 |
Design and Programming, D | A | 7 |
Documentation, E | D | 1 |
Draft and Preparation of report, F | B | 6 |
Compilation of report, G | E, F | 1 |
Final checking, H | G | 1 |
Preparation of presentation, I | G | 1 |