Activity Precedence Table
| Activity | Immediate Predecessor | Duration Planned (weeks) |
| Team formation, A | - | 1 |
| Determination of nature of business, B | A | 1 |
| Planning, Requirement and Design, C | B | 3 |
| Design and Programming, D | A | 7 |
| Documentation, E | D | 1 |
| Draft and Preparation of report, F | B | 6 |
| Compilation of report, G | E, F | 1 |
| Final checking, H | G | 1 |
| Preparation of presentation, I | G | 1 |